CP 71-635-017 - 2018-Reconditioning CR 35Central Specialties Inc Minnesota Paving & Materials Knife River Corporation Duininck Inc North Valley Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$100,000.00$100,000.00$96,000.00$96,000.00$85,000.00$85,000.00$58,000.00$58,000.00$64,431.13$64,431.13
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$0.01$0.01$1.00$1.00$1,597.47$1,597.47
2104.501REMOVE GUARDRAILL F91$20.00$1,820.00$16.00$1,456.00$10.00$910.00$200.00$18,200.00$37.27$3,391.57
2104.501REMOVE PIPE CULVERTSLIN FT872$9.41$8,205.52$11.00$9,592.00$15.00$13,080.00$15.15$13,210.80$8.04$7,010.88
2104.503REMOVE RETAINING WALLS F644$10.00$6,440.00$4.55$2,930.20$4.00$2,576.00$4.00$2,576.00$4.26$2,743.44
2104.503REMOVE BITUMINOUS DRIVEWAY PAVEMENTS F3,464$1.00$3,464.00$1.10$3,810.40$1.40$4,849.60$0.75$2,598.00$0.37$1,281.68
2104.505REMOVE BITUMINOUS PAVEMENTS Y37,605$1.20$45,126.00$0.50$18,802.50$1.20$45,126.00$0.99$37,228.95$2.08$78,218.40
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F153$4.00$612.00$2.25$344.25$3.00$459.00$4.00$612.00$3.19$488.07
2104.523SALVAGE MAIL BOX SUPPORTEACH42$35.00$1,470.00$36.00$1,512.00$35.00$1,470.00$35.00$1,470.00$37.27$1,565.34
2104.523SALVAGE FIRE NUMBEREACH41$35.00$1,435.00$36.00$1,476.00$35.00$1,435.00$35.00$1,435.00$37.27$1,528.07
2104.523SALVAGE CULVERT MARKEREACH12$20.00$240.00$67.50$810.00$15.00$180.00$75.00$900.00$37.27$447.24
2105.501COMMON EXCAVATION (EV) (P)CU YD8,804$5.37$47,277.48$6.35$55,905.40$11.00$96,844.00$11.11$97,812.44$9.85$86,719.40
2105.522SELECT GRANULAR BORROW (CV)C Y3,500$16.01$56,035.00$17.50$61,250.00$1.00$3,500.00$1.00$3,500.00$14.48$50,680.00
2123.509DOZER TYPE D4 OR EQUIVALENTHOUR20$136.36$2,727.20$145.00$2,900.00$125.00$2,500.00$126.00$2,520.00$159.75$3,195.00
2130.501WATERMGAL200$40.00$8,000.00$24.50$4,900.00$1.00$200.00$1.00$200.00$37.27$7,454.00
2211.501AGGREGATE BASE CLASS 5 (P)TON16,643$10.59$176,249.37$8.40$139,801.20$11.65$193,890.95$12.60$209,701.80$7.99$132,977.57
2221.609SHOULDER BASE AGGREGATE SPECIALTON1,370$16.55$22,673.50$25.00$34,250.00$13.85$18,974.50$11.65$15,960.50$29.89$40,949.30
2232.501MILL BITUMINOUS SURFACESQ YD87$15.00$1,305.00$4.70$408.90$19.00$1,653.00$10.00$870.00$7.30$635.10
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON4,030$48.53$195,575.90$65.00$261,950.00$53.00$213,590.00$54.91$221,287.30$58.61$236,198.30
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,C)TON4,903$47.98$235,245.94$52.00$254,956.00$48.00$235,344.00$49.58$243,090.74$49.85$244,414.55
2411.618MODULAR BLOCK RETAINING WALLS F644$24.74$15,932.56$28.50$18,354.00$28.00$18,032.00$24.50$15,778.00$26.35$16,969.40
2501.51136" RC PIPE CULVERTL F387$130.66$50,565.42$120.00$46,440.00$125.00$48,375.00$126.00$48,762.00$122.47$47,395.89
2501.51124" CP PIPE CULVERTL F30$43.55$1,306.50$67.00$2,010.00$50.00$1,500.00$50.50$1,515.00$31.42$942.60
2501.51118" RC PIPE CULVERTL F83$162.65$13,499.95$70.50$5,851.50$45.00$3,735.00$45.45$3,772.35$44.73$3,712.59
2501.51118" CP PIPE CULVERTL F324$70.90$22,971.60$43.50$14,094.00$40.00$12,960.00$40.40$13,089.60$24.76$8,022.24
2501.51536" RC PIPE APRONEACH2$1,025.36$2,050.72$2,300.00$4,600.00$1,550.00$3,100.00$1,565.00$3,130.00$2,076.71$4,153.42
2501.51518" RC PIPE APRONEACH2$743.18$1,486.36$1,350.00$2,700.00$900.00$1,800.00$900.00$1,800.00$931.86$1,863.72
2501.51518" CS PIPE APRONEACH8$201.47$1,611.76$455.00$3,640.00$400.00$3,200.00$404.00$3,232.00$239.62$1,916.96
2501.56724" CS SAFETY APR & GRATE DES 3128EACH2$1,069.31$2,138.62$1,450.00$2,900.00$1,500.00$3,000.00$1,515.00$3,030.00$1,208.75$2,417.50
2501.56718" RC SAFETY APRON & GRATE DES 3128EACH1$1,488.97$1,488.97$1,650.00$1,650.00$1,750.00$1,750.00$1,700.00$1,700.00$2,209.83$2,209.83
2501.573INSTALL CULVERT MARKEREACH14$50.00$700.00$110.00$1,540.00$25.00$350.00$100.00$1,400.00$117.15$1,640.10
2503.602CONNECT TO EXISTING STORM SEWEREACH1$2,000.00$2,000.00$580.00$580.00$750.00$750.00$750.00$750.00$2,129.95$2,129.95
2506.501CONST DRAINAGE STRUCTURE DES 48-4020L F5$509.30$2,546.50$2,500.00$12,500.00$450.00$2,250.00$450.00$2,250.00$479.24$2,396.20
2506.516CASTING ASSEMBLYEACH1$500.00$500.00$730.00$730.00$850.00$850.00$858.00$858.00$724.19$724.19
2511.501RANDOM RIPRAP CLASS IIC Y32$80.00$2,560.00$110.00$3,520.00$110.00$3,520.00$111.00$3,552.00$90.52$2,896.64
2540.602MAIL BOX SUPPORTEACH33$110.00$3,630.00$115.00$3,795.00$110.00$3,630.00$110.00$3,630.00$37.27$1,229.91
2540.602RELOCATE MAIL BOXEACH9$35.00$315.00$36.00$324.00$35.00$315.00$35.00$315.00$37.27$335.43
2557.602TEMPORARY MAILBOX SUPPORTEACH42$40.00$1,680.00$41.50$1,743.00$40.00$1,680.00$40.00$1,680.00$42.60$1,789.20
2563.601DETOUR SIGNINGLS1$1,300.00$1,300.00$1,300.00$1,300.00$5,600.00$5,600.00$3,695.00$3,695.00$1,384.47$1,384.47
2563.601TRAFFIC CONTROLLS1$4,000.00$4,000.00$4,000.00$4,000.00$2,300.00$2,300.00$2,200.00$2,200.00$4,259.91$4,259.91
2564.602INSTALL STEEL POSTEACH3$37.50$112.50$39.00$117.00$37.50$112.50$37.50$112.50$39.94$119.82
2573.502SILT FENCE, TYPE MSL F6,484$1.60$10,374.40$1.60$10,374.40$1.50$9,726.00$1.60$10,374.40$2.08$13,486.72
2573.533SEDIMENT CONTROL LOG TYPE COMPOSTL F2,524$1.95$4,921.80$1.95$4,921.80$1.50$3,786.00$1.95$4,921.80$2.34$5,906.16
2573.560CULVERT END CONTROLSEACH14$75.00$1,050.00$65.00$910.00$150.00$2,100.00$75.00$1,050.00$228.97$3,205.58
2573.601STORM WATER MANAGEMENTLS1$2,000.00$2,000.00$2,000.00$2,000.00$2,100.00$2,100.00$15,000.00$15,000.00$3,727.42$3,727.42
2573.610SEDIMENT REMOVALHOUR20$200.00$4,000.00$265.00$5,300.00$1.00$20.00$30.00$600.00$1.07$21.40
2574.508FERTILIZER TYPE 1LB1,748$0.50$874.00$0.50$874.00$0.65$1,136.20$0.50$874.00$0.52$908.96
2574.525COMMON TOPSOIL BORROWC Y100$40.00$4,000.00$47.00$4,700.00$1.00$100.00$1.00$100.00$25.03$2,503.00
2574.578SOIL BED PREPARATIONACRE9$85.00$765.00$85.00$765.00$50.00$450.00$85.00$765.00$367.42$3,306.78
2575.501SEEDINGACRE9$65.00$585.00$65.00$585.00$100.00$900.00$65.00$585.00$133.12$1,198.08
2575.502SEED MIXTURE 25-121LB533$3.45$1,838.85$3.45$1,838.85$3.95$2,105.35$3.45$1,838.85$3.89$2,073.37
2575.502SEED MIXTURE 21-111LB437$0.45$196.65$0.45$196.65$0.75$327.75$0.45$196.65$1.17$511.29
2575.560HYDRAULIC MATRIX, TYPE MULCHLB17,480$0.60$10,488.00$0.60$10,488.00$0.30$5,244.00$0.60$10,488.00$0.73$12,760.40
2575.560HYDRAULIC MATRIX, TYPE BONDED FIBERLB30,590$0.80$24,472.00$0.80$24,472.00$1.00$30,590.00$0.80$24,472.00$0.99$30,284.10
2582.5024" DOUBLE SOLID LINE-PAINTL F7,328$0.126$923.33$0.15$1,099.20$0.15$1,099.20$0.13$952.64$0.16$1,172.48
2582.5024" BROKEN LINE-PAINTL F5,996$0.013$77.95$0.07$419.72$0.02$119.92$0.01$59.96$0.02$119.92
2582.5024" SOLID LINE-PAINTL F31,506$0.063$1,984.88$0.07$2,205.42$0.07$2,205.42$0.06$1,890.36$0.08$2,520.48
 Totals for project CP 71-635-017 $1,114,851.23 $1,156,594.39 $1,102,401.40 $1,121,594.64 $1,158,142.62
 
CP 71-611-018 - 2018-Reconditioning CSAH 11Central Specialties Inc Minnesota Paving & Materials Knife River Corporation Duininck Inc North Valley Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$200,000.00$200,000.00$102,000.00$102,000.00$145,000.00$145,000.00$173,800.00$173,800.00$129,927.24$129,927.24
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$0.01$0.01$1.00$1.00$1,597.47$1,597.47
2104.501REMOVE PIPE CULVERTSL F668$7.70$5,143.60$7.00$4,676.00$12.00$8,016.00$12.12$8,096.16$6.39$4,268.52
2104.503REMOVE BITUMINOUS DRIVEWAY PAVEMENTS F4,656$0.88$4,097.28$0.80$3,724.80$1.40$6,518.40$0.76$3,538.56$0.37$1,722.72
2104.503REMOVE CONCRETE DRIVEWAY PAVEMENTS F618$1.10$679.80$1.00$618.00$0.95$587.10$1.51$933.18$1.22$753.96
2104.505REMOVE BITUMINOUS PAVEMENTS Y78,398$1.80$141,116.40$1.85$145,036.30$2.10$164,635.80$2.55$199,914.90$1.97$154,444.06
2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH)L F13$3.30$42.90$4.75$61.75$9.00$117.00$10.10$131.30$6.92$89.96
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F155$3.30$511.50$2.25$348.75$3.00$465.00$4.04$626.20$3.04$471.20
2104.523SALVAGE MAIL BOX SUPPORTEACH4$35.00$140.00$36.00$144.00$35.00$140.00$35.00$140.00$37.28$149.12
2104.523SALVAGE FIRE NUMBEREACH18$22.00$396.00$20.00$360.00$35.00$630.00$35.00$630.00$37.27$670.86
2104.523SALVAGE CULVERT MARKEREACH8$22.00$176.00$20.00$160.00$15.00$120.00$75.00$600.00$37.27$298.16
2105.501COMMON EXCAVATION (EV) (P)CU YD58,346$4.81$280,644.26$4.45$259,639.70$7.00$408,422.00$7.07$412,506.22$8.15$475,519.90
2105.522SELECT GRANULAR BORROW (CV)C Y1,540$16.02$24,670.80$14.50$22,330.00$15.00$23,100.00$15.15$23,331.00$15.60$24,024.00
2123.509DOZER TYPE D4 OR EQUIVALENTHOUR20$132.00$2,640.00$120.00$2,400.00$125.00$2,500.00$126.00$2,520.00$159.75$3,195.00
2130.501WATERMGAL500$22.00$11,000.00$20.00$10,000.00$25.00$12,500.00$25.25$12,625.00$37.27$18,635.00
2211.501AGGREGATE BASE CLASS 5 (P)TON89,302$9.25$826,043.50$8.55$763,532.10$10.65$951,066.30$10.60$946,601.20$9.32$832,294.64
2221.609SHOULDER BASE AGGREGATE SPECIALTON3,495$13.29$46,448.55$12.00$41,940.00$13.85$48,405.75$13.21$46,168.95$30.36$106,108.20
2232.501MILL BITUMINOUS SURFACES Y90$15.00$1,350.00$5.00$450.00$19.00$1,710.00$10.00$900.00$7.30$657.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,C)TON12,744$44.20$563,284.80$51.50$656,316.00$48.00$611,712.00$51.42$655,296.48$52.11$664,089.84
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON13,134$44.75$587,746.50$53.00$696,102.00$53.00$696,102.00$56.81$746,142.54$59.61$782,917.74
2451.509AGGREGATE BEDDING (CV)C Y30$28.60$858.00$26.00$780.00$50.00$1,500.00$50.50$1,515.00$31.95$958.50
2501.51115" CP PIPE CULVERTL F171$36.41$6,226.11$33.00$5,643.00$30.00$5,130.00$30.30$5,181.30$20.77$3,551.67
2501.51115" RC PIPE CULVERT CLASS IIIL F380$85.21$32,379.80$77.50$29,450.00$40.00$15,200.00$40.40$15,352.00$42.60$16,188.00
2501.51118" CP PIPE CULVERTL F194$37.60$7,294.40$34.00$6,596.00$40.00$7,760.00$40.40$7,837.60$23.96$4,648.24
2501.51518" CS PIPE APRONEACH2$187.00$374.00$170.00$340.00$400.00$800.00$404.00$808.00$239.62$479.24
2501.51515" RC PIPE APRONEACH1$638.00$638.00$580.00$580.00$850.00$850.00$858.00$858.00$825.36$825.36
2501.51515" CS PIPE APRONEACH2$165.00$330.00$150.00$300.00$350.00$700.00$354.00$708.00$213.00$426.00
2501.519FLAP GATE FOR 15" RC PIPEEACH1$770.00$770.00$700.00$700.00$1,000.00$1,000.00$1,000.00$1,000.00$878.60$878.60
2501.56718" CS SAFETY APR & GRATE DES 3128EACH4$660.00$2,640.00$600.00$2,400.00$850.00$3,400.00$858.00$3,432.00$692.24$2,768.96
2501.573INSTALL CULVERT MARKEREACH10$22.00$220.00$20.00$200.00$25.00$250.00$100.00$1,000.00$106.50$1,065.00
2506.602CONNECT INTO EXISTING DRAINAGE STRUCTUREEACH2$1,650.00$3,300.00$1,500.00$3,000.00$750.00$1,500.00$757.00$1,514.00$2,289.71$4,579.42
2531.5076" CONCRETE DRIVEWAY PAVEMENTS Y79$75.00$5,925.00$60.00$4,740.00$81.00$6,399.00$100.00$7,900.00$63.90$5,048.10
2540.602RELOCATE MAIL BOXEACH4$35.00$140.00$36.00$144.00$35.00$140.00$35.00$140.00$37.28$149.12
2540.602MAIL BOX SUPPORTEACH18$110.00$1,980.00$115.00$2,070.00$110.00$1,980.00$110.00$1,980.00$117.15$2,108.70
2545.5231.25" NON-METALLIC CONDUITL F53,540$4.14$221,655.60$3.70$198,098.00$3.70$198,098.00$3.70$198,098.00$4.23$226,474.20
2550.513JUNCTION BOXEACH12$246.47$2,957.64$45.00$540.00$45.00$540.00$45.00$540.00$51.47$617.64
2550.514FIBEROPTIC SPLICE VAULTEACH12$1,089.06$13,068.72$1,100.00$13,200.00$1,117.00$13,404.00$1,117.00$13,404.00$1,277.47$15,329.64
2550.516BURIED CABLE SIGNEACH12$129.84$1,558.08$130.00$1,560.00$35.00$420.00$35.00$420.00$40.03$480.36
2557.602TEMPORARY MAILBOX SUPPORTEACH22$40.00$880.00$41.50$913.00$40.00$880.00$40.00$880.00$42.60$937.20
2563.601TRAFFIC CONTROLLS1$4,600.00$4,600.00$4,600.00$4,600.00$3,700.00$3,700.00$3,875.00$3,875.00$4,898.90$4,898.90
2563.601DETOUR SIGNINGLS1$4,700.00$4,700.00$4,700.00$4,700.00$9,300.00$9,300.00$5,895.00$5,895.00$5,005.39$5,005.39
2564.602INSTALL STEEL POSTEACH2$37.50$75.00$39.00$78.00$37.50$75.00$37.50$75.00$39.94$79.88
2573.502SILT FENCE, TYPE MSL F31,663$1.60$50,660.80$1.60$50,660.80$1.50$47,494.50$1.60$50,660.80$2.08$65,859.04
2573.533SEDIMENT CONTROL LOG TYPE COMPOSTL F24,645$1.95$48,057.75$1.95$48,057.75$1.50$36,967.50$1.95$48,057.75$2.34$57,669.30
2573.560CULVERT END CONTROLSEACH8$75.00$600.00$100.00$800.00$150.00$1,200.00$75.00$600.00$239.62$1,916.96
2573.601STORM WATER MANAGEMENTLS1$2,000.00$2,000.00$2,000.00$2,000.00$2,100.00$2,100.00$15,000.00$15,000.00$3,727.42$3,727.42
2573.610SEDIMENT REMOVALHOUR20$110.00$2,200.00$100.00$2,000.00$1.00$20.00$30.00$600.00$1.07$21.40
2574.508FERTILIZER TYPE 1LB3,070$0.50$1,535.00$0.50$1,535.00$0.65$1,995.50$0.50$1,535.00$0.52$1,596.40
2574.525COMMON TOPSOIL BORROWC Y100$20.90$2,090.00$19.00$1,900.00$1.00$100.00$1.00$100.00$26.62$2,662.00
2574.578SOIL BED PREPARATIONACRE15.4$85.00$1,309.00$85.00$1,309.00$50.00$770.00$85.00$1,309.00$367.42$5,658.27
2575.501SEEDINGACRE15.4$65.00$1,001.00$65.00$1,001.00$100.00$1,540.00$65.00$1,001.00$133.12$2,050.05
2575.502SEED MIXTURE 25-121LB936$3.45$3,229.20$3.45$3,229.20$3.95$3,697.20$3.45$3,229.20$3.89$3,641.04
2575.502SEED MIXTURE 21-111LB768$0.45$345.60$0.45$345.60$0.75$576.00$0.45$345.60$1.17$898.56
2575.560HYDRAULIC MATRIX, TYPE BONDED FIBERLB53,725$0.80$42,980.00$0.80$42,980.00$1.00$53,725.00$0.80$42,980.00$0.99$53,187.75
2575.560HYDRAULIC MATRIX, TYPE MULCHLB30,700$0.60$18,420.00$0.60$18,420.00$0.30$9,210.00$0.60$18,420.00$0.73$22,411.00
2582.5024" BROKEN LINE-PAINTL F20,295$0.013$263.84$0.07$1,420.65$0.02$405.90$0.01$202.95$0.02$405.90
2582.5024" SOLID LINE-PAINTL F56,972$0.063$3,589.24$0.07$3,988.04$0.07$3,988.04$0.06$3,418.32$0.08$4,557.76
2582.5024" DOUBLE SOLID LINE-PAINTL F7,022$0.126$884.77$0.15$1,053.30$0.15$1,053.30$0.12$842.64$0.16$1,123.52
 Totals for project CP 71-611-018 $3,187,869.44 $3,171,172.74 $3,519,616.30 $3,695,217.85 $3,726,719.08
 
TWP 10-2018-01 - 2018-Big Lake Township-Whitewater EstatesCentral Specialties Inc Minnesota Paving & Materials Knife River Corporation Duininck Inc North Valley Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2357.502BITUMINOUS MATERIAL FOR TACK COATGAL1,350$3.00$4,050.00$2.35$3,172.50$1.80$2,430.00$2.50$3,375.00$2.82$3,807.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON2,162$47.49$102,673.38$47.00$101,614.00$47.00$101,614.00$46.65$100,857.30$47.17$101,981.54
2563.601TRAFFIC CONTROLLS1$1,400.00$1,400.00$1,400.00$1,400.00$600.00$600.00$1,000.00$1,000.00$1,490.96$1,490.96
 Totals for project TWP 10-2018-01 $108,123.38 $106,186.50 $104,644.00 $105,232.30 $107,279.50
 
Contract Total:$4,410,844.05$4,433,953.63$4,726,661.70$4,922,044.79$4,992,141.20