Contract Bid Abstract

CP 71-655-017 - 2018-CR 55 from Moorhouse Ave to Hwy 10Knife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$5,600.00$5,600.00$22,250.00$22,250.00$2,290.00$2,290.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$0.01$0.01$1.00$1.00$12.10$12.10
2104.523SALVAGE MAIL BOX SUPPORTEACH4$65.00$260.00$65.18$260.72$66.00$264.00
2211.501AGGREGATE BASE CLASS 5 - DRIVEWAYSTON325$11.80$3,835.00$13.03$4,234.75$30.40$9,880.00
2221.609SHOULDER BASE AGGREGATE SPECIALTON581$11.80$6,855.80$17.69$10,277.89$26.40$15,338.40
2232.501MILL BITUMINOUS SURFACES Y28$9.00$252.00$17.16$480.48$10.50$294.00
2360.501TYPE SP 4.75 WEARING COURSE MIX (2,B)TON915$48.00$43,920.00$45.50$41,632.50$60.60$55,449.00
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON1,846$48.00$88,608.00$46.00$84,916.00$58.00$107,068.00
2540.602MAIL BOX SUPPORTEACH4$120.00$480.00$120.32$481.28$122.00$488.00
2563.601TRAFFIC CONTROLLS1$2,300.00$2,300.00$1,900.00$1,900.00$711.00$711.00
2582.5024" SOLID LINE-PAINTL F19,020$0.05$951.00$0.05$951.00$0.05$951.00
2582.5024" BROKEN LINE-PAINTL F2,883$0.05$144.15$0.05$144.15$0.05$144.15
 Totals for project CP 71-655-017 $153,205.96 $167,529.77 $192,889.65
 
CP 71-656-017 - 2018-CR 56 from Hwy 10 to CR 53 & CR 54 Reclaim/OverlayKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$5,600.00$5,600.00$24,000.00$24,000.00$2,290.00$2,290.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$0.01$0.01$1.00$1.00$12.10$12.10
2104.523SALVAGE MAIL BOX SUPPORTEACH8$65.00$520.00$65.17$521.36$66.00$528.00
2211.501AGGREGATE BASE CLASS 5 - DRIVEWAYSTON585$11.80$6,903.00$13.29$7,774.65$28.30$16,555.50
2221.609SHOULDER BASE AGGREGATE SPECIALTON597$11.80$7,044.60$17.69$10,560.93$26.40$15,760.80
2232.501MILL BITUMINOUS SURFACES Y40$9.00$360.00$17.14$685.60$10.50$420.00
2360.501TYPE SP 4.75 WEARING COURSE MIX (2,B)TON1,580$48.00$75,840.00$44.50$70,310.00$60.20$95,116.00
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON3,234$48.00$155,232.00$46.00$148,764.00$57.10$184,661.40
2540.602MAIL BOX SUPPORTEACH8$120.00$960.00$120.32$962.56$122.00$976.00
2563.601TRAFFIC CONTROLLS1$2,300.00$2,300.00$2,000.00$2,000.00$711.00$711.00
2582.5024" SOLID LINE-PAINTL F35,675$0.05$1,783.75$0.05$1,783.75$0.05$1,783.75
2582.5024" BROKEN LINE-PAINTL F1,704$0.05$85.20$0.05$85.20$0.05$85.20
 Totals for project CP 71-656-017 $256,628.56 $267,449.05 $318,899.75
 
CP 71-658-017 - 2018-CR 58 from CSAH 8 to Church St Reclaim/OverlayKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$5,600.00$5,600.00$23,975.71$23,975.71$5,070.00$5,070.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$0.01$0.01$1.00$1.00$121.00$121.00
2104.523SALVAGE MAIL BOX SUPPORTEACH9$65.00$585.00$65.17$586.53$66.00$594.00
2211.501AGGREGATE BASE CLASS 5 - DRIVEWAYSTON570$11.80$6,726.00$13.03$7,427.10$32.00$18,240.00
2221.609SHOULDER BASE AGGREGATE SPECIALTON820$11.80$9,676.00$17.69$14,505.80$26.40$21,648.00
2232.501MILL BITUMINOUS SURFACES Y40$9.00$360.00$17.14$685.60$10.50$420.00
2360.501TYPE SP 4.75 WEARING COURSE MIX (2,B)TON1,290$48.00$61,920.00$45.00$58,050.00$60.20$77,658.00
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON2,613$48.00$125,424.00$45.50$118,891.50$57.70$150,770.10
2540.602MAIL BOX SUPPORTEACH9$120.00$1,080.00$120.32$1,082.88$122.00$1,098.00
2545.5231.25" NON-METALLIC CONDUITL F23,000$3.36$77,280.00$3.36$77,280.00$2.55$58,650.00
2550.513JUNCTION BOXEACH6$233.35$1,400.10$233.35$1,400.10$584.00$3,504.00
2550.514FIBEROPTIC SPLICE VAULTEACH6$1,017.01$6,102.06$1,017.01$6,102.06$1,160.00$6,960.00
2550.516BURIED CABLE SIGNEACH6$134.62$807.72$134.62$807.72$152.00$912.00
2563.601TRAFFIC CONTROLLS1$2,300.00$2,300.00$2,300.00$2,300.00$711.00$711.00
2582.5024" SOLID LINE-PAINTL F31,156$0.05$1,557.80$0.05$1,557.80$0.05$1,557.80
2582.5024" BROKEN LINE-PAINTL F1,769$0.05$88.45$0.05$88.45$0.05$88.45
 Totals for project CP 71-658-017 $300,907.14 $314,742.25 $348,002.35
 
CP 71-642-017 - 2018-CR 42 from CSAH 9 North to CSAH 1Knife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$5,600.00$5,600.00$13,600.00$13,600.00$2,290.00$2,290.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$0.01$0.01$1.00$1.00$12.10$12.10
2104.523SALVAGE MAIL BOX SUPPORTEACH35$65.00$2,275.00$65.17$2,280.95$66.00$2,310.00
2211.501AGGREGATE BASE CLASS 5 - DRIVEWAYSTON570$11.80$6,726.00$11.53$6,572.10$25.70$14,649.00
2221.609SHOULDER BASE AGGREGATE SPECIALTON2,180$11.80$25,724.00$16.33$35,599.40$21.70$47,306.00
2232.501MILL BITUMINOUS SURFACES Y96$9.00$864.00$17.15$1,646.40$10.50$1,008.00
2360.501TYPE SP 4.75 WEARING COURSE MIX (2,B)TON1,880$48.00$90,240.00$47.00$88,360.00$55.40$104,152.00
2360.501TYPE SP 9.5 WEARING COURSE MIX (2,C)TON3,854$48.00$184,992.00$47.50$183,065.00$55.60$214,282.40
2540.602MAIL BOX SUPPORTEACH35$120.00$4,200.00$120.32$4,211.20$122.00$4,270.00
2563.601TRAFFIC CONTROLLS1$2,300.00$2,300.00$2,200.00$2,200.00$711.00$711.00
2582.5024" SOLID LINE-PAINTL F38,817$0.05$1,940.85$0.05$1,940.85$0.05$1,940.85
2582.5024" BROKEN LINE-PAINTL F2,950$0.05$147.50$0.05$147.50$0.05$147.50
 Totals for project CP 71-642-017 $325,009.36 $339,624.40 $393,078.85
 
TWP 01-2018-01 - 2018-Baldwin Township-136th StreetKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$1,800.00$1,800.00$10,000.00$10,000.00$3,080.00$3,080.00
2221.501AGGREGATE SHOULDERING CLASS 5TON835$16.35$13,652.25$14.04$11,723.40$17.10$14,278.50
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON3,335$44.00$146,740.00$41.00$136,735.00$45.20$150,742.00
2563.601TRAFFIC CONTROLLS1$800.00$800.00$1,000.00$1,000.00$711.00$711.00
2582.5024" SOLID LINE-PAINTL F26,158$0.05$1,307.90$0.05$1,307.90$0.05$1,307.90
2582.5024" DOUBLE SOLID LINE-PAINTL F13,079$0.10$1,307.90$0.10$1,307.90$0.10$1,307.90
 Totals for project TWP 01-2018-01 $165,608.05 $162,074.20 $171,427.30
 
TWP 05-2018-01 - 2018-Becker Township -185th AvenueKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$2,400.00$2,400.00$9,200.00$9,200.00$7,000.00$7,000.00
2118.501AGGREGATE SURFACING CLASS 5TON4,219.22$13.35$56,326.59$12.67$53,457.52$15.90$67,085.60
2118.501AGGREGATE SURFACING CLASS 1TON500$16.35$8,175.00$15.04$7,520.00$35.20$17,600.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON4,026.88$43.00$173,155.84$41.50$167,115.52$45.00$181,209.60
2531.501CONCRETE CURB & GUTTER DESIGN D412 (MOD)L F406$20.00$8,120.00$20.05$8,140.30$26.80$10,880.80
 Totals for project TWP 05-2018-01 $248,177.43 $245,433.34 $283,776.00
 
TWP 20-2018-01 - 2018-Clear Lake Township - 97th StreetKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$1,200.00$1,200.00$4,200.00$4,200.00$2,730.00$2,730.00
2221.501AGGREGATE SHOULDERING CLASS 5TON200$16.35$3,270.00$17.05$3,410.00$18.70$3,740.00
2232.603MILL BIT PAVEMENT FOR CRACK REPAIRL F90$7.00$630.00$17.16$1,544.40$65.50$5,895.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON710$42.00$29,820.00$44.00$31,240.00$48.60$34,506.00
2563.601TRAFFIC CONTROLLS1$400.00$400.00$671.80$671.80$711.00$711.00
 Totals for project TWP 20-2018-01 $35,320.00 $41,066.20 $47,582.00
 
TWP 30-2018-01 - 2018-Livonia Township - 112th StreetKnife River Corporation Minnesota Paving & Materials Park Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$1,800.00$1,800.00$5,800.00$5,800.00$4,920.00$4,920.00
2221.501SHOULDER BASE AGGREGATE CLASS 6BTON742$14.45$10,721.90$18.29$13,571.18$19.00$14,098.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON2,344$45.00$105,480.00$42.00$98,448.00$52.20$122,356.80
2563.601TRAFFIC CONTROLLS1$800.00$800.00$376.01$376.01$711.00$711.00
2582.5024" SOLID LINE WHITE-PAINTL F20,590$0.05$1,029.50$0.10$2,059.00$0.05$1,029.50
2582.5024" DOUBLE SOLID LINE-PAINTL F10,295$0.10$1,029.50$0.10$1,029.50$0.10$1,029.50
 Totals for project TWP 30-2018-01 $120,860.90 $121,283.69 $144,144.80
 
Contract Total:$1,605,717.40$1,659,202.90$1,899,800.70