CP 71-635-017 - 2018-Reconditioning CR 35 | Central Specialties Inc | Minnesota Paving & Materials | Knife River Corporation | Duininck Inc | North Valley Inc |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2021.501 | MOBILIZATION | LS | 1 | $100,000.00 | $100,000.00 | $96,000.00 | $96,000.00 | $85,000.00 | $85,000.00 | $58,000.00 | $58,000.00 | $64,431.13 | $64,431.13 |
2051.501 | MAINT & RESTORATION OF HAUL ROADS | LS | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 | $0.01 | $1.00 | $1.00 | $1,597.47 | $1,597.47 |
2104.501 | REMOVE GUARDRAIL | L F | 91 | $20.00 | $1,820.00 | $16.00 | $1,456.00 | $10.00 | $910.00 | $200.00 | $18,200.00 | $37.27 | $3,391.57 |
2104.501 | REMOVE PIPE CULVERTS | LIN FT | 872 | $9.41 | $8,205.52 | $11.00 | $9,592.00 | $15.00 | $13,080.00 | $15.15 | $13,210.80 | $8.04 | $7,010.88 |
2104.503 | REMOVE BITUMINOUS DRIVEWAY PAVEMENT | S F | 3,464 | $1.00 | $3,464.00 | $1.10 | $3,810.40 | $1.40 | $4,849.60 | $0.75 | $2,598.00 | $0.37 | $1,281.68 |
2104.503 | REMOVE RETAINING WALL | S F | 644 | $10.00 | $6,440.00 | $4.55 | $2,930.20 | $4.00 | $2,576.00 | $4.00 | $2,576.00 | $4.26 | $2,743.44 |
2104.505 | REMOVE BITUMINOUS PAVEMENT | S Y | 37,605 | $1.20 | $45,126.00 | $0.50 | $18,802.50 | $1.20 | $45,126.00 | $0.99 | $37,228.95 | $2.08 | $78,218.40 |
2104.513 | SAWING BIT PAVEMENT (FULL DEPTH) | L F | 153 | $4.00 | $612.00 | $2.25 | $344.25 | $3.00 | $459.00 | $4.00 | $612.00 | $3.19 | $488.07 |
2104.523 | SALVAGE MAIL BOX SUPPORT | EACH | 42 | $35.00 | $1,470.00 | $36.00 | $1,512.00 | $35.00 | $1,470.00 | $35.00 | $1,470.00 | $37.27 | $1,565.34 |
2104.523 | SALVAGE CULVERT MARKER | EACH | 12 | $20.00 | $240.00 | $67.50 | $810.00 | $15.00 | $180.00 | $75.00 | $900.00 | $37.27 | $447.24 |
2104.523 | SALVAGE FIRE NUMBER | EACH | 41 | $35.00 | $1,435.00 | $36.00 | $1,476.00 | $35.00 | $1,435.00 | $35.00 | $1,435.00 | $37.27 | $1,528.07 |
2105.501 | COMMON EXCAVATION (EV) (P) | CU YD | 8,804 | $5.37 | $47,277.48 | $6.35 | $55,905.40 | $11.00 | $96,844.00 | $11.11 | $97,812.44 | $9.85 | $86,719.40 |
2105.522 | SELECT GRANULAR BORROW (CV) | C Y | 3,500 | $16.01 | $56,035.00 | $17.50 | $61,250.00 | $1.00 | $3,500.00 | $1.00 | $3,500.00 | $14.48 | $50,680.00 |
2123.509 | DOZER TYPE D4 OR EQUIVALENT | HOUR | 20 | $136.36 | $2,727.20 | $145.00 | $2,900.00 | $125.00 | $2,500.00 | $126.00 | $2,520.00 | $159.75 | $3,195.00 |
2130.501 | WATER | MGAL | 200 | $40.00 | $8,000.00 | $24.50 | $4,900.00 | $1.00 | $200.00 | $1.00 | $200.00 | $37.27 | $7,454.00 |
2211.501 | AGGREGATE BASE CLASS 5 (P) | TON | 16,643 | $10.59 | $176,249.37 | $8.40 | $139,801.20 | $11.65 | $193,890.95 | $12.60 | $209,701.80 | $7.99 | $132,977.57 |
2221.609 | SHOULDER BASE AGGREGATE SPECIAL | TON | 1,370 | $16.55 | $22,673.50 | $25.00 | $34,250.00 | $13.85 | $18,974.50 | $11.65 | $15,960.50 | $29.89 | $40,949.30 |
2232.501 | MILL BITUMINOUS SURFACE | SQ YD | 87 | $15.00 | $1,305.00 | $4.70 | $408.90 | $19.00 | $1,653.00 | $10.00 | $870.00 | $7.30 | $635.10 |
2360.501 | TYPE SP 9.5 WEARING COURSE MIX (2,C) | TON | 4,030 | $48.53 | $195,575.90 | $65.00 | $261,950.00 | $53.00 | $213,590.00 | $54.91 | $221,287.30 | $58.61 | $236,198.30 |
2360.501 | TYPE SP 12.5 WEARING COURSE MIX (2,C) | TON | 4,903 | $47.98 | $235,245.94 | $52.00 | $254,956.00 | $48.00 | $235,344.00 | $49.58 | $243,090.74 | $49.85 | $244,414.55 |
2411.618 | MODULAR BLOCK RETAINING WALL | S F | 644 | $24.74 | $15,932.56 | $28.50 | $18,354.00 | $28.00 | $18,032.00 | $24.50 | $15,778.00 | $26.35 | $16,969.40 |
2501.511 | 18" RC PIPE CULVERT | L F | 83 | $162.65 | $13,499.95 | $70.50 | $5,851.50 | $45.00 | $3,735.00 | $45.45 | $3,772.35 | $44.73 | $3,712.59 |
2501.511 | 18" CP PIPE CULVERT | L F | 324 | $70.90 | $22,971.60 | $43.50 | $14,094.00 | $40.00 | $12,960.00 | $40.40 | $13,089.60 | $24.76 | $8,022.24 |
2501.511 | 36" RC PIPE CULVERT | L F | 387 | $130.66 | $50,565.42 | $120.00 | $46,440.00 | $125.00 | $48,375.00 | $126.00 | $48,762.00 | $122.47 | $47,395.89 |
2501.511 | 24" CP PIPE CULVERT | L F | 30 | $43.55 | $1,306.50 | $67.00 | $2,010.00 | $50.00 | $1,500.00 | $50.50 | $1,515.00 | $31.42 | $942.60 |
2501.515 | 36" RC PIPE APRON | EACH | 2 | $1,025.36 | $2,050.72 | $2,300.00 | $4,600.00 | $1,550.00 | $3,100.00 | $1,565.00 | $3,130.00 | $2,076.71 | $4,153.42 |
2501.515 | 18" RC PIPE APRON | EACH | 2 | $743.18 | $1,486.36 | $1,350.00 | $2,700.00 | $900.00 | $1,800.00 | $900.00 | $1,800.00 | $931.86 | $1,863.72 |
2501.515 | 18" CS PIPE APRON | EACH | 8 | $201.47 | $1,611.76 | $455.00 | $3,640.00 | $400.00 | $3,200.00 | $404.00 | $3,232.00 | $239.62 | $1,916.96 |
2501.567 | 24" CS SAFETY APR & GRATE DES 3128 | EACH | 2 | $1,069.31 | $2,138.62 | $1,450.00 | $2,900.00 | $1,500.00 | $3,000.00 | $1,515.00 | $3,030.00 | $1,208.75 | $2,417.50 |
2501.567 | 18" RC SAFETY APRON & GRATE DES 3128 | EACH | 1 | $1,488.97 | $1,488.97 | $1,650.00 | $1,650.00 | $1,750.00 | $1,750.00 | $1,700.00 | $1,700.00 | $2,209.83 | $2,209.83 |
2501.573 | INSTALL CULVERT MARKER | EACH | 14 | $50.00 | $700.00 | $110.00 | $1,540.00 | $25.00 | $350.00 | $100.00 | $1,400.00 | $117.15 | $1,640.10 |
2503.602 | CONNECT TO EXISTING STORM SEWER | EACH | 1 | $2,000.00 | $2,000.00 | $580.00 | $580.00 | $750.00 | $750.00 | $750.00 | $750.00 | $2,129.95 | $2,129.95 |
2506.501 | CONST DRAINAGE STRUCTURE DES 48-4020 | L F | 5 | $509.30 | $2,546.50 | $2,500.00 | $12,500.00 | $450.00 | $2,250.00 | $450.00 | $2,250.00 | $479.24 | $2,396.20 |
2506.516 | CASTING ASSEMBLY | EACH | 1 | $500.00 | $500.00 | $730.00 | $730.00 | $850.00 | $850.00 | $858.00 | $858.00 | $724.19 | $724.19 |
2511.501 | RANDOM RIPRAP CLASS II | C Y | 32 | $80.00 | $2,560.00 | $110.00 | $3,520.00 | $110.00 | $3,520.00 | $111.00 | $3,552.00 | $90.52 | $2,896.64 |
2540.602 | MAIL BOX SUPPORT | EACH | 33 | $110.00 | $3,630.00 | $115.00 | $3,795.00 | $110.00 | $3,630.00 | $110.00 | $3,630.00 | $37.27 | $1,229.91 |
2540.602 | RELOCATE MAIL BOX | EACH | 9 | $35.00 | $315.00 | $36.00 | $324.00 | $35.00 | $315.00 | $35.00 | $315.00 | $37.27 | $335.43 |
2557.602 | TEMPORARY MAILBOX SUPPORT | EACH | 42 | $40.00 | $1,680.00 | $41.50 | $1,743.00 | $40.00 | $1,680.00 | $40.00 | $1,680.00 | $42.60 | $1,789.20 |
2563.601 | TRAFFIC CONTROL | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $2,300.00 | $2,300.00 | $2,200.00 | $2,200.00 | $4,259.91 | $4,259.91 |
2563.601 | DETOUR SIGNING | LS | 1 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 | $5,600.00 | $5,600.00 | $3,695.00 | $3,695.00 | $1,384.47 | $1,384.47 |
2564.602 | INSTALL STEEL POST | EACH | 3 | $37.50 | $112.50 | $39.00 | $117.00 | $37.50 | $112.50 | $37.50 | $112.50 | $39.94 | $119.82 |
2573.502 | SILT FENCE, TYPE MS | L F | 6,484 | $1.60 | $10,374.40 | $1.60 | $10,374.40 | $1.50 | $9,726.00 | $1.60 | $10,374.40 | $2.08 | $13,486.72 |
2573.533 | SEDIMENT CONTROL LOG TYPE COMPOST | L F | 2,524 | $1.95 | $4,921.80 | $1.95 | $4,921.80 | $1.50 | $3,786.00 | $1.95 | $4,921.80 | $2.34 | $5,906.16 |
2573.560 | CULVERT END CONTROLS | EACH | 14 | $75.00 | $1,050.00 | $65.00 | $910.00 | $150.00 | $2,100.00 | $75.00 | $1,050.00 | $228.97 | $3,205.58 |
2573.601 | STORM WATER MANAGEMENT | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,100.00 | $2,100.00 | $15,000.00 | $15,000.00 | $3,727.42 | $3,727.42 |
2573.610 | SEDIMENT REMOVAL | HOUR | 20 | $200.00 | $4,000.00 | $265.00 | $5,300.00 | $1.00 | $20.00 | $30.00 | $600.00 | $1.07 | $21.40 |
2574.508 | FERTILIZER TYPE 1 | LB | 1,748 | $0.50 | $874.00 | $0.50 | $874.00 | $0.65 | $1,136.20 | $0.50 | $874.00 | $0.52 | $908.96 |
2574.525 | COMMON TOPSOIL BORROW | C Y | 100 | $40.00 | $4,000.00 | $47.00 | $4,700.00 | $1.00 | $100.00 | $1.00 | $100.00 | $25.03 | $2,503.00 |
2574.578 | SOIL BED PREPARATION | ACRE | 9 | $85.00 | $765.00 | $85.00 | $765.00 | $50.00 | $450.00 | $85.00 | $765.00 | $367.42 | $3,306.78 |
2575.501 | SEEDING | ACRE | 9 | $65.00 | $585.00 | $65.00 | $585.00 | $100.00 | $900.00 | $65.00 | $585.00 | $133.12 | $1,198.08 |
2575.502 | SEED MIXTURE 21-111 | LB | 437 | $0.45 | $196.65 | $0.45 | $196.65 | $0.75 | $327.75 | $0.45 | $196.65 | $1.17 | $511.29 |
2575.502 | SEED MIXTURE 25-121 | LB | 533 | $3.45 | $1,838.85 | $3.45 | $1,838.85 | $3.95 | $2,105.35 | $3.45 | $1,838.85 | $3.89 | $2,073.37 |
2575.560 | HYDRAULIC MATRIX, TYPE MULCH | LB | 17,480 | $0.60 | $10,488.00 | $0.60 | $10,488.00 | $0.30 | $5,244.00 | $0.60 | $10,488.00 | $0.73 | $12,760.40 |
2575.560 | HYDRAULIC MATRIX, TYPE BONDED FIBER | LB | 30,590 | $0.80 | $24,472.00 | $0.80 | $24,472.00 | $1.00 | $30,590.00 | $0.80 | $24,472.00 | $0.99 | $30,284.10 |
2582.502 | 4" DOUBLE SOLID LINE-PAINT | L F | 7,328 | $0.126 | $923.33 | $0.15 | $1,099.20 | $0.15 | $1,099.20 | $0.13 | $952.64 | $0.16 | $1,172.48 |
2582.502 | 4" SOLID LINE-PAINT | L F | 31,506 | $0.063 | $1,984.88 | $0.07 | $2,205.42 | $0.07 | $2,205.42 | $0.06 | $1,890.36 | $0.08 | $2,520.48 |
2582.502 | 4" BROKEN LINE-PAINT | L F | 5,996 | $0.013 | $77.95 | $0.07 | $419.72 | $0.02 | $119.92 | $0.01 | $59.96 | $0.02 | $119.92 |
| Totals for project CP 71-635-017 | | $1,114,851.23 | | $1,156,594.39 | | $1,102,401.40 | | $1,121,594.64 | | $1,158,142.62 |
|
CP 71-611-018 - 2018-Reconditioning CSAH 11 | Central Specialties Inc | Minnesota Paving & Materials | Knife River Corporation | Duininck Inc | North Valley Inc |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2021.501 | MOBILIZATION | LS | 1 | $200,000.00 | $200,000.00 | $102,000.00 | $102,000.00 | $145,000.00 | $145,000.00 | $173,800.00 | $173,800.00 | $129,927.24 | $129,927.24 |
2051.501 | MAINT & RESTORATION OF HAUL ROADS | LS | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 | $0.01 | $1.00 | $1.00 | $1,597.47 | $1,597.47 |
2104.501 | REMOVE PIPE CULVERTS | L F | 668 | $7.70 | $5,143.60 | $7.00 | $4,676.00 | $12.00 | $8,016.00 | $12.12 | $8,096.16 | $6.39 | $4,268.52 |
2104.503 | REMOVE BITUMINOUS DRIVEWAY PAVEMENT | S F | 4,656 | $0.88 | $4,097.28 | $0.80 | $3,724.80 | $1.40 | $6,518.40 | $0.76 | $3,538.56 | $0.37 | $1,722.72 |
2104.503 | REMOVE CONCRETE DRIVEWAY PAVEMENT | S F | 618 | $1.10 | $679.80 | $1.00 | $618.00 | $0.95 | $587.10 | $1.51 | $933.18 | $1.22 | $753.96 |
2104.505 | REMOVE BITUMINOUS PAVEMENT | S Y | 78,398 | $1.80 | $141,116.40 | $1.85 | $145,036.30 | $2.10 | $164,635.80 | $2.55 | $199,914.90 | $1.97 | $154,444.06 |
2104.511 | SAWING CONCRETE PAVEMENT (FULL DEPTH) | L F | 13 | $3.30 | $42.90 | $4.75 | $61.75 | $9.00 | $117.00 | $10.10 | $131.30 | $6.92 | $89.96 |
2104.513 | SAWING BIT PAVEMENT (FULL DEPTH) | L F | 155 | $3.30 | $511.50 | $2.25 | $348.75 | $3.00 | $465.00 | $4.04 | $626.20 | $3.04 | $471.20 |
2104.523 | SALVAGE MAIL BOX SUPPORT | EACH | 4 | $35.00 | $140.00 | $36.00 | $144.00 | $35.00 | $140.00 | $35.00 | $140.00 | $37.28 | $149.12 |
2104.523 | SALVAGE CULVERT MARKER | EACH | 8 | $22.00 | $176.00 | $20.00 | $160.00 | $15.00 | $120.00 | $75.00 | $600.00 | $37.27 | $298.16 |
2104.523 | SALVAGE FIRE NUMBER | EACH | 18 | $22.00 | $396.00 | $20.00 | $360.00 | $35.00 | $630.00 | $35.00 | $630.00 | $37.27 | $670.86 |
2105.501 | COMMON EXCAVATION (EV) (P) | CU YD | 58,346 | $4.81 | $280,644.26 | $4.45 | $259,639.70 | $7.00 | $408,422.00 | $7.07 | $412,506.22 | $8.15 | $475,519.90 |
2105.522 | SELECT GRANULAR BORROW (CV) | C Y | 1,540 | $16.02 | $24,670.80 | $14.50 | $22,330.00 | $15.00 | $23,100.00 | $15.15 | $23,331.00 | $15.60 | $24,024.00 |
2123.509 | DOZER TYPE D4 OR EQUIVALENT | HOUR | 20 | $132.00 | $2,640.00 | $120.00 | $2,400.00 | $125.00 | $2,500.00 | $126.00 | $2,520.00 | $159.75 | $3,195.00 |
2130.501 | WATER | MGAL | 500 | $22.00 | $11,000.00 | $20.00 | $10,000.00 | $25.00 | $12,500.00 | $25.25 | $12,625.00 | $37.27 | $18,635.00 |
2211.501 | AGGREGATE BASE CLASS 5 (P) | TON | 89,302 | $9.25 | $826,043.50 | $8.55 | $763,532.10 | $10.65 | $951,066.30 | $10.60 | $946,601.20 | $9.32 | $832,294.64 |
2221.609 | SHOULDER BASE AGGREGATE SPECIAL | TON | 3,495 | $13.29 | $46,448.55 | $12.00 | $41,940.00 | $13.85 | $48,405.75 | $13.21 | $46,168.95 | $30.36 | $106,108.20 |
2232.501 | MILL BITUMINOUS SURFACE | S Y | 90 | $15.00 | $1,350.00 | $5.00 | $450.00 | $19.00 | $1,710.00 | $10.00 | $900.00 | $7.30 | $657.00 |
2360.501 | TYPE SP 12.5 WEARING COURSE MIX (2,C) | TON | 12,744 | $44.20 | $563,284.80 | $51.50 | $656,316.00 | $48.00 | $611,712.00 | $51.42 | $655,296.48 | $52.11 | $664,089.84 |
2360.501 | TYPE SP 9.5 WEARING COURSE MIX (2,C) | TON | 13,134 | $44.75 | $587,746.50 | $53.00 | $696,102.00 | $53.00 | $696,102.00 | $56.81 | $746,142.54 | $59.61 | $782,917.74 |
2451.509 | AGGREGATE BEDDING (CV) | C Y | 30 | $28.60 | $858.00 | $26.00 | $780.00 | $50.00 | $1,500.00 | $50.50 | $1,515.00 | $31.95 | $958.50 |
2501.511 | 18" CP PIPE CULVERT | L F | 194 | $37.60 | $7,294.40 | $34.00 | $6,596.00 | $40.00 | $7,760.00 | $40.40 | $7,837.60 | $23.96 | $4,648.24 |
2501.511 | 15" RC PIPE CULVERT CLASS III | L F | 380 | $85.21 | $32,379.80 | $77.50 | $29,450.00 | $40.00 | $15,200.00 | $40.40 | $15,352.00 | $42.60 | $16,188.00 |
2501.511 | 15" CP PIPE CULVERT | L F | 171 | $36.41 | $6,226.11 | $33.00 | $5,643.00 | $30.00 | $5,130.00 | $30.30 | $5,181.30 | $20.77 | $3,551.67 |
2501.515 | 15" CS PIPE APRON | EACH | 2 | $165.00 | $330.00 | $150.00 | $300.00 | $350.00 | $700.00 | $354.00 | $708.00 | $213.00 | $426.00 |
2501.515 | 15" RC PIPE APRON | EACH | 1 | $638.00 | $638.00 | $580.00 | $580.00 | $850.00 | $850.00 | $858.00 | $858.00 | $825.36 | $825.36 |
2501.515 | 18" CS PIPE APRON | EACH | 2 | $187.00 | $374.00 | $170.00 | $340.00 | $400.00 | $800.00 | $404.00 | $808.00 | $239.62 | $479.24 |
2501.519 | FLAP GATE FOR 15" RC PIPE | EACH | 1 | $770.00 | $770.00 | $700.00 | $700.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $878.60 | $878.60 |
2501.567 | 18" CS SAFETY APR & GRATE DES 3128 | EACH | 4 | $660.00 | $2,640.00 | $600.00 | $2,400.00 | $850.00 | $3,400.00 | $858.00 | $3,432.00 | $692.24 | $2,768.96 |
2501.573 | INSTALL CULVERT MARKER | EACH | 10 | $22.00 | $220.00 | $20.00 | $200.00 | $25.00 | $250.00 | $100.00 | $1,000.00 | $106.50 | $1,065.00 |
2506.602 | CONNECT INTO EXISTING DRAINAGE STRUCTURE | EACH | 2 | $1,650.00 | $3,300.00 | $1,500.00 | $3,000.00 | $750.00 | $1,500.00 | $757.00 | $1,514.00 | $2,289.71 | $4,579.42 |
2531.507 | 6" CONCRETE DRIVEWAY PAVEMENT | S Y | 79 | $75.00 | $5,925.00 | $60.00 | $4,740.00 | $81.00 | $6,399.00 | $100.00 | $7,900.00 | $63.90 | $5,048.10 |
2540.602 | MAIL BOX SUPPORT | EACH | 18 | $110.00 | $1,980.00 | $115.00 | $2,070.00 | $110.00 | $1,980.00 | $110.00 | $1,980.00 | $117.15 | $2,108.70 |
2540.602 | RELOCATE MAIL BOX | EACH | 4 | $35.00 | $140.00 | $36.00 | $144.00 | $35.00 | $140.00 | $35.00 | $140.00 | $37.28 | $149.12 |
2545.523 | 1.25" NON-METALLIC CONDUIT | L F | 53,540 | $4.14 | $221,655.60 | $3.70 | $198,098.00 | $3.70 | $198,098.00 | $3.70 | $198,098.00 | $4.23 | $226,474.20 |
2550.513 | JUNCTION BOX | EACH | 12 | $246.47 | $2,957.64 | $45.00 | $540.00 | $45.00 | $540.00 | $45.00 | $540.00 | $51.47 | $617.64 |
2550.514 | FIBEROPTIC SPLICE VAULT | EACH | 12 | $1,089.06 | $13,068.72 | $1,100.00 | $13,200.00 | $1,117.00 | $13,404.00 | $1,117.00 | $13,404.00 | $1,277.47 | $15,329.64 |
2550.516 | BURIED CABLE SIGN | EACH | 12 | $129.84 | $1,558.08 | $130.00 | $1,560.00 | $35.00 | $420.00 | $35.00 | $420.00 | $40.03 | $480.36 |
2557.602 | TEMPORARY MAILBOX SUPPORT | EACH | 22 | $40.00 | $880.00 | $41.50 | $913.00 | $40.00 | $880.00 | $40.00 | $880.00 | $42.60 | $937.20 |
2563.601 | TRAFFIC CONTROL | LS | 1 | $4,600.00 | $4,600.00 | $4,600.00 | $4,600.00 | $3,700.00 | $3,700.00 | $3,875.00 | $3,875.00 | $4,898.90 | $4,898.90 |
2563.601 | DETOUR SIGNING | LS | 1 | $4,700.00 | $4,700.00 | $4,700.00 | $4,700.00 | $9,300.00 | $9,300.00 | $5,895.00 | $5,895.00 | $5,005.39 | $5,005.39 |
2564.602 | INSTALL STEEL POST | EACH | 2 | $37.50 | $75.00 | $39.00 | $78.00 | $37.50 | $75.00 | $37.50 | $75.00 | $39.94 | $79.88 |
2573.502 | SILT FENCE, TYPE MS | L F | 31,663 | $1.60 | $50,660.80 | $1.60 | $50,660.80 | $1.50 | $47,494.50 | $1.60 | $50,660.80 | $2.08 | $65,859.04 |
2573.533 | SEDIMENT CONTROL LOG TYPE COMPOST | L F | 24,645 | $1.95 | $48,057.75 | $1.95 | $48,057.75 | $1.50 | $36,967.50 | $1.95 | $48,057.75 | $2.34 | $57,669.30 |
2573.560 | CULVERT END CONTROLS | EACH | 8 | $75.00 | $600.00 | $100.00 | $800.00 | $150.00 | $1,200.00 | $75.00 | $600.00 | $239.62 | $1,916.96 |
2573.601 | STORM WATER MANAGEMENT | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,100.00 | $2,100.00 | $15,000.00 | $15,000.00 | $3,727.42 | $3,727.42 |
2573.610 | SEDIMENT REMOVAL | HOUR | 20 | $110.00 | $2,200.00 | $100.00 | $2,000.00 | $1.00 | $20.00 | $30.00 | $600.00 | $1.07 | $21.40 |
2574.508 | FERTILIZER TYPE 1 | LB | 3,070 | $0.50 | $1,535.00 | $0.50 | $1,535.00 | $0.65 | $1,995.50 | $0.50 | $1,535.00 | $0.52 | $1,596.40 |
2574.525 | COMMON TOPSOIL BORROW | C Y | 100 | $20.90 | $2,090.00 | $19.00 | $1,900.00 | $1.00 | $100.00 | $1.00 | $100.00 | $26.62 | $2,662.00 |
2574.578 | SOIL BED PREPARATION | ACRE | 15.4 | $85.00 | $1,309.00 | $85.00 | $1,309.00 | $50.00 | $770.00 | $85.00 | $1,309.00 | $367.42 | $5,658.27 |
2575.501 | SEEDING | ACRE | 15.4 | $65.00 | $1,001.00 | $65.00 | $1,001.00 | $100.00 | $1,540.00 | $65.00 | $1,001.00 | $133.12 | $2,050.05 |
2575.502 | SEED MIXTURE 25-121 | LB | 936 | $3.45 | $3,229.20 | $3.45 | $3,229.20 | $3.95 | $3,697.20 | $3.45 | $3,229.20 | $3.89 | $3,641.04 |
2575.502 | SEED MIXTURE 21-111 | LB | 768 | $0.45 | $345.60 | $0.45 | $345.60 | $0.75 | $576.00 | $0.45 | $345.60 | $1.17 | $898.56 |
2575.560 | HYDRAULIC MATRIX, TYPE BONDED FIBER | LB | 53,725 | $0.80 | $42,980.00 | $0.80 | $42,980.00 | $1.00 | $53,725.00 | $0.80 | $42,980.00 | $0.99 | $53,187.75 |
2575.560 | HYDRAULIC MATRIX, TYPE MULCH | LB | 30,700 | $0.60 | $18,420.00 | $0.60 | $18,420.00 | $0.30 | $9,210.00 | $0.60 | $18,420.00 | $0.73 | $22,411.00 |
2582.502 | 4" SOLID LINE-PAINT | L F | 56,972 | $0.063 | $3,589.24 | $0.07 | $3,988.04 | $0.07 | $3,988.04 | $0.06 | $3,418.32 | $0.08 | $4,557.76 |
2582.502 | 4" DOUBLE SOLID LINE-PAINT | L F | 7,022 | $0.126 | $884.77 | $0.15 | $1,053.30 | $0.15 | $1,053.30 | $0.12 | $842.64 | $0.16 | $1,123.52 |
2582.502 | 4" BROKEN LINE-PAINT | L F | 20,295 | $0.013 | $263.84 | $0.07 | $1,420.65 | $0.02 | $405.90 | $0.01 | $202.95 | $0.02 | $405.90 |
| Totals for project CP 71-611-018 | | $3,187,869.44 | | $3,171,172.74 | | $3,519,616.30 | | $3,695,217.85 | | $3,726,719.08 |
|
TWP 10-2018-01 - 2018-Big Lake Township-Whitewater Estates | Central Specialties Inc | Minnesota Paving & Materials | Knife River Corporation | Duininck Inc | North Valley Inc |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2357.502 | BITUMINOUS MATERIAL FOR TACK COAT | GAL | 1,350 | $3.00 | $4,050.00 | $2.35 | $3,172.50 | $1.80 | $2,430.00 | $2.50 | $3,375.00 | $2.82 | $3,807.00 |
2360.501 | TYPE SP 12.5 WEARING COURSE MIX (2,B) | TON | 2,162 | $47.49 | $102,673.38 | $47.00 | $101,614.00 | $47.00 | $101,614.00 | $46.65 | $100,857.30 | $47.17 | $101,981.54 |
2563.601 | TRAFFIC CONTROL | LS | 1 | $1,400.00 | $1,400.00 | $1,400.00 | $1,400.00 | $600.00 | $600.00 | $1,000.00 | $1,000.00 | $1,490.96 | $1,490.96 |
| Totals for project TWP 10-2018-01 | | $108,123.38 | | $106,186.50 | | $104,644.00 | | $105,232.30 | | $107,279.50 |
|
Contract Total: | $4,410,844.05 | $4,433,953.63 | $4,726,661.70 | $4,922,044.79 | $4,992,141.20 |